Gervais Bond Construction Update - August 2025

We’re making exciting progress across our schools, thanks to your support of the bond! Here’s the latest:

Elementary School

  • Exterior work is 100% complete

  • Ceiling work will wrap up by the end of August

Middle School

  • Subcontractor bids received August 5th and presented to the School District

  • Early excavation work begins mid-September

High School

  • Roofing work completed this summer

  • Sheet metal work done by the end of August

Looking Ahead to September

Elementary School – Punch list and demobilizing until next summer’s construction

Middle School – Early grading and ground improvements begin

High School – Punch list and demobilizing until next summer’s construction

🪏Join Us for the Groundbreaking Ceremony!

Tuesday, September 10 at 5:30 PM

Gervais Middle School

Bring your family, grab a gold shovel, snap a photo, and help us celebrate this exciting milestone. Kids are encouraged to join in the fun.

View the Construction Update PDF here

Learn more about the Gervais bond at our Gervais School District Bond website https://www.gervaisbond.org/

Next
Next

Gervais Bond Construction Update - July 2025