Gervais Construction Update | August 2026

August 2026 Gervais Bond construction update with photos of the Elementary School exterior, Middle School under construction, and finished High School gym.

🏗️ Gervais Construction Update: August

August was a big one. Crews put in serious hours to get summer projects wrapped before the first bell, and by the end of the month, more than $4 million of work was in the books. Here's where things stand:

Elementary & High School: the home stretch 🎉

Every area of the project is in final trim out. Exterior painting is 85% done and should hit 100% in the next couple of weeks. Punch list walkthroughs have started, with site clean-up and demobilization right behind. Translation: we're close.

Middle School: building by building 🔨

Building 1 is being handed over. Over at Building 4, mechanical, electrical, and plumbing rough-in is 80% complete, and the roof and windows are going in. Polished concrete, site utilities, and curbs? Done. In September, look for paving, site concrete, drywall, and more exterior siding.

Big thanks to the crews who spent their summer making these spaces ready for students.

August 2026 Gervais Bond construction update with photos of the Elementary School exterior, Middle School under construction, and finished High School gym.
Next
Next

Gervais Construction Update | July 2026