February Construction Update

Bond Construction Update

The district continues to make progress on bond-funded construction projects at the Elementary School, Middle School, and High School. Below is the latest update on current work, temporary changes, and what to expect next.

Elementary School

Construction on the front entry and administrative office area will begin over Spring Break. The rest of this work will continue during Summer 2026.

This project includes:

  • A new secure and accessible front entry vestibule

  • Upgrades to the existing front entry

  • Improvements to the administrative office area

  • Renovations to student restrooms

  • Exterior building refresh work

During construction, the school’s main entry will temporarily move to the side entrance.

Temporary Entry for Elementary School Students

As construction begins at the Elementary School, all kindergarten through fifth grade students will enter and exit the building through the east side doors starting on the first day of the temporary change.

For student drop-off and pick-up, families should continue using the designated car zone.

Middle School

Progress continues at the Middle School.

Current work includes:

  • Concrete pour scheduled for March 23

  • Underground plumbing work underway

  • Underground fire sprinkler work underway

  • Underground electrical work underway

High School

Several improvement projects are moving forward at the High School.

Current work includes:

  • Gym HVAC work will take place after basketball season and special events are complete

  • Construction on the locker room and new weight room project began on March 2

Reader Board and Signage Project

The district’s new reader board has been installed.

Construction took place during the last week of February. The district is now completing the training and registration process needed to begin using the new sign.

Looking Ahead

Here is what is coming next across the district:

Elementary School

A series of renovation projects will begin construction in March.

Middle School

Concrete work is expected to begin on March 23.

High School

The district will review high school improvement bids and begin construction on approved renovation projects.